Crews have been scraping, digging, and leveling earth for just over a month now, and Phase 1 of Altona's industrial park expansion is progressing well. That's the latest update from Mayor Harv Schroeder.

"Fast Brothers are living up to their name. They are working quickly and effectively so far," he explained. "The last update that we received is that they are continuing to put in the manholes and sewer lines. They are also making progress on the retention pond which is necessary for drainage of the development."

The goal, he added, is to carve out the roads and install the water, sewer, and drainage system by the end of March.

"And then spring will set in, it'll get messy there so, as far as I understand, they'll be doing the lift station after spring."

Overall, Schroeder says Council is encouraged by the interest that's been expressed so far in the available lots in Phase 1. The hope is that this project will lead to new and/or expanded local businesses, which Schroeder says will lead to more jobs and growth. 