Work is well underway on the reconstruction of the southbound lanes of Highway 75 between Morris and St. Jean
Portal
Title Image Caption
Work is well underway on the reconstruction of the southbound lanes of Highway 75 between Morris and St. Jean
Categories

According to a Provincial spokesperson, the reconstruction of the southbound lanes of Highway 75 between Morris and St. Jean is progressing on schedule. The 8.34km project includes concrete work and shoulder widening.

Three kilometers of concrete pavement will be applied by the end of the 2024 construction season with the remainder being completed during next year's construction season. Manitoba Transportation and Infrastructure anticipates the entire project will be completed by Fall 2025.

Meanwhile, surface rehabilitation work on the southbound lanes of Highway 75 in various locations between the south junction of Highway 23 and Provincial Road 205 is expected to be completed this Fall.