Work is progressing on Highway 27 through Sundre.
Progress to Date
The detour road opened on schedule April 3 for westbound traffic.
Drivers are reminded to slow down and use caution as the route runs through a residential area.
Revised traffic and pedestrian accommodations are now in place at 2nd and 4th Streets NW.
The electrical conduit crossing at Centre Street is complete, with electrical on going.
Grading, placing gravel and formwork is ongoing at the south side of 1st Street NW, to the access to Burger Baron.
Sidewalk and curb have been poured on the south side of 5th Street NW, at the creek.
A mountable curb at the barrier wall on 9th Street NE is complete.
What’s Coming Next
Highway 27 & 760 intersection: Cleaning, grading, gravel placement, and concrete forming and pouring at the corners of the intersection. Landscaping and repairs will take place mid-April.
Centre Street: Grading and forming curbs and sidewalks.
4th Street NW: Installation of streetlight bases continues.
Sidewalk preparation, including forming and pouring of concrete, will be taking place throughout the coming week at 2nd, 4th, and Centre Streets.
Reminder: Speed limits stay at 30 km/h in the construction zone — even if crews aren’t working — and fines double in construction zones.
Click here for further updates
Sign up to get the latest local news headlines delivered directly to your inbox every afternoon.
Send your news tips, story ideas, pictures, and videos to news@centralalbertaonline.com.
CentralAlbertaOnline encourages you to get your news directly from your trusted source by bookmarking this page and downloading the CentralAlbertaOnline app.