Lacombe County has released a schedule of this summer's paving. The county has contracted Central City Asphalt Ltd. to pave the following roads:
- Rge Rd 24 (Eagle’s Quay) (Schedule “F”) from Hwy 11A to Eagle’s Quay Subdivision for 6.728 km and Pelican Bay Access Road for 0.08 km, starting June 2.
- Prentiss Road (Rge Rd 260) (Schedule “E”) from Hwy 597 to Lakeside Sargent Road for 6.640 km, starting July 2.
- Meridian Road (Rge Rd 10) & Brighton Beach Road (Schedule “D”) from Hwy 12A to the east end of Brighton Beach Road for 2.235 km, starting July 6.
- Sandy Point Access Road (Schedule “C”), starting July 8.
- from Rge Rd 11 to the “T” Intersection for 1.534 km
- from the “T” Intersection to the Beach Access for 0.147 km
- from the “T intersection to the South Parking Lot for 0.407 km
- Sunbreaker Cove (Rge Rd 22) (Schedule “B”) from the Boat Launch to Rainy Creek Road for 2.122 km, starting July 10.
- Eckville West (Twp Rd 393) & Eckville North (Rge Rd 35) (Schedule “A”) from 53 St to Rainy Creek Road for 7.087 km, starting June 16.
All work is expected to be completed by the second week of July (weather permitting). Work will include asphalt concrete pavement (EPS) and other work. Please contact the Operations department with any questions or concerns regarding this project.
Please drive with caution around construction crews and obey all signage.
**with information provided by Lacombe County
Sign up to get the latest local news headlines delivered directly to your inbox every afternoon.
Send your news tips, story ideas, pictures, and videos to news@centralalbertaonline.com.
CentralAlbertaOnline encourages you to get your news directly from your trusted source by bookmarking this page and downloading the CentralAlbertaOnline app.