Beginning on Monday 15, until further notice, there will be a traffic detour associated with the 40th Avenue overpass.
According to the city of Airdrie, the North Bridge deck at 40 Avenue and Southpoint LD-CPR Overpass will be closed.
"Traffic will be detoured onto the new (south) bridge deck to accommodate construction on the existing (north) bridge deck," the city stated on their website.
The next milestones for the project are forecast to be completed in the summer months.
This includes the completion of the South Point Access Roadwork to be finished by the end of June 2023, as well as the completion of the 40th Ave Roadwork in mid-July, and the finishing of the 40th Avenue bridge over the QEII by the end of July.
The construction is expected to be finished in October 2023.